|
The Movers Are Here Are You
Ready?
So, you are moving offices. You know
it is going to involve a lot of effort and a lot of planning. How
prepared are you? Have you given yourself enough time to organize
the move, and then have you taken the time to plan it well? Have you
done everything you need to in preparation for the move? If you are
really prepared, then everything other than the actual move was done
days ago.
Nearly every growing business moves
at least once. TNS has been involved with countless office and data
center moves over the years, and we have found there are several key
considerations that make moves easier and less interruptive and
therefore less costly both financially and emotionally.
It
seems that no matter how hard one tries, people procrastinate, and
moving tasks get pushed to the last minute; this is always the
number one cause of issues on moving day.
If possible, start planning 6 months
prior to your targeted move date. If 6 months is not feasible
because of any reasons, give yourself as much time as possible.
Having the plan in place is more important than how much time you
may or may not have. One rule of thumb is that you need all plans
finalized and contracts in place a minimum of 6 to 8 weeks prior to
the planned move date. Of course, these plans must take into
account the timeframe you have got to work within: how much time do
you have before your move?
A plan done 6 weeks ahead that
requires 8 weeks to execute is obviously not going to work unless
you change the date of the move. This error is easier to make than
you might imagine. The challenge about plans is that until certain
tasks are done, the duration of a particular activity may be
unknown. You may not know how long you need to accomplish something
until you have finished it! Perhaps one of the first things you need
to assess is what you know how much you can estimate and foresee
regarding the steps required to accomplish a particular milestone.
Because of the difficulty of
estimating correctly and how crucial these estimates can be to a
successful move, if at all possible, you should get expert help with
planning your move. Experience counts for something, but you should
always take into account the element of unpredictability. Sometimes
the experience of others can differ from your real experience. When
possible, get details, as many as you can.
Build a project plan showing as much
detail as you can; break it into resources for all future
participants in the move.
Microsoft Project is a good tool if
you know how to use it (very easy for projects large and small) but
at a minimum, create a calendar (preferably in electronic format)
and mark the resources on it with a timeline for each.
Good project planning can expose
conflicting milestones. A couple of examples: if the floor cannot be
walked on for a period of time, then other projects cannot be
completed during that time. Doing a 10-day job in 7 normal work
days means a crew is going to be working either two Sundays and a
Saturday or two Saturdays and a Sunday.
Here is our high level project plan
outline covering facility side of the issues for your reference:
 |
Building Considerations |
 |
Room Considerations |
 |
Flooring |
 |
Ceiling & Lighting |
 |
Power Distribution & Protection |
 |
HVAC Considerations |
 |
Fire Suppression |
 |
Moisture/Leak Detection |
 |
Data / Voice Cabling Placement |
 |
Racks & Furniture Placement |
 |
Monitoring & Management |
 |
Physical Site Security |
 |
Disaster Avoidance & Recovery |
All the work orders need to be
completed ahead of time if you plan to use a General Contractor,
Architect, or other key professionals. They all need to be aware of
the timeline you are working with. And expect that everyone will
take longer than anticipated, so plan more time than you estimate
you need a good rule of thumb is to increase time and resources by
25%.
Here is how our project contacts
usually look like:
 |
Facility Owner / Agent |
 |
Site Executive |
 |
City & Other Permit Departments |
 |
IT / Facilities Manager |
 |
Building Facilities Management
Contacts |
 |
Architect |
 |
General Contractor |
 |
Electrician |
 |
Mechanical Engineer |
 |
Cabling Contractor |
 |
Construction Contractor |
 |
Fire Protection Contractor |
 |
Utility Company Contact |
 |
Telco Contact |
 |
Furniture Suppliers |
 |
Moving Company Contact |
 |
Cleaning Services |
 |
Off-site Media Storage |
We also recommend that you plan for
your new location to be ready at least two days prior to your move
in. If at all possible, move all of your data and telecommunication
services at least 1 day prior to your move. Typically, you can make
alternate arrangements: for example, phone calls can be forwarded to
cell phones for a day.
Make sure the data service at the old
site is not brought down until after the move. Go one step further
and arrange it so that for a short period of time, both your old and
your new sites are active at the same time. This lets you test the
new site for your data and Telco (Telephone Company) capabilities
before the actual move. I have unfortunately seen businesses try to
save a few dollars by cutting over on the day of their move and end
up being down or finding themselves at a vastly reduced level of
service for up to two weeks due an unanticipated failure of one or
more of the participants or resources.
Try to discover if vendors can
actually meet their commitments, and do not tolerate it if they do
not live up to their own timetables.
Is the physical space ready? Make
sure you have verified that everything that you know you need is
going to be in place. Recently, we had a client whose landlord did
not hire a General Contractor so he decided to manage the tear-down,
build-out and contracted tenant improvements himself. Upon first
entry after the initial build-out, we noticed there was no Minimal
Point of Entry (MPOE) for the data and telephone equipment. It been
ripped out in the tear-down phase but had not been replaced in the
build-out phase. And to add to the problem, the municipal telephone
company in the city where this occurred required at least 1 month
putting a new MPOE in. However, in our inspection, we found this
out when the building was still being worked on, several weeks ahead
of the move. The landlord was not pleased when they had to pay rush
charges and the unanticipated cost of the MPOE. But our client was
very happy that they could move in when scheduled.
Are there enough electrical outlets
with the right type of interface and specifications? Will the
outlets need to be dedicated or shared? Are data and telephone
locations in the right places? In many cases, doubling the number
of outlets or jack for data and telephone typically will be a 1/3
increase in cost. Post-move installs are far more expensive and
disruptive.
Is the physical space organized by
room or other location designation so that items can be tagged with
a number to indicate their target destination?
Is your new address clear, or will
vendors who may come to your facility only once have difficulty
finding you? Whoever is managing the subcontractor needs to be there
when they show up. We had a situation recently where a telephone
company came out to install a data line, but the suite number they
had was wrong, so when they went in and asked if the occupants had
ordered a line, they where told no. Of course, they canceled the
order, and our client discovered that it actually took longer to get
a reorder than it did an original installation since it had to go
though the whole system twice.
What about your furniture do you
know where all your furniture is going to go? It is great if you
can get new furniture with your new location. This makes your move
much easier because you do not have to move as much, and you can
have the new location set-up ahead of time.
Of course, it is not always possible
to get new furniture along with your move, but the more you can
actually see the space with the furniture in it, the better off you
are. The biggest and most disruptive aspect of moving in to your
new space is how the cables and power will run to the equipment
where they are needed. The moment cables or wire have to run across
a floor, they become a hazard. Monuments are a data/power/Telco
hookup normally flush mounted in the middle of where furniture is
anticipated to be. This is very nice when the furniture ends up
being where it was planned, not so good when it does not. Sometimes
the best solution is to pre-run cables to the furniture layout, and
mocks the furniture locations. Use chalk on floor, butcher paper
cutouts whatever works for you, but please, whatever you do, try
to figure out and confirm furniture placement ahead of time. If you
can visualize well then maybe drawings are sufficient, but do not
just figure out where the furniture will go, figure out where the
power cords and cables will go also.
Last but not least there are a few items that are absolutely
necessary in order to get everything up and running. Power strips
are a classic example. The computer, telephone and furniture have
arrived, but there is no way to make them work with the two outlets
nearby. So, place crucial items in special boxes that are tracked
separately from the others. Power strips, for example, do not need a
room number so they can be placed in a box marked Power Strips DO
NOT STACK ITEMS ON TOP OF THIS BOX. Few things are more
frustrating than having to rummage through boxes looking for the
small items you need to get operational.
So now you should be a little closer
to saying, Sure I am prepared
been that way for days. Hopefully we have provided some information
that saved you some time, money and emotional distress.
By
Jerry Ware,
IT
Solutions Fellow
Back to Top 
Information Request Form
|